XOCEAN set to survey Bellrock export cable corridor
-
27 July 2026
-
Cables, Vessels, Windfarms
-
Bellrock Offshore Wind Farm Ltd

XOCEAN is set to undertake a geophysical survey within a potential offshore
export cable corridor associated with the 1.8GW Bellrock
floating offshore wind
project in Scotland.
The campaign is scheduled to commence no earlier than 26 July 2026 and
is expected to require approximately 60 operational days. Work may continue
until 30 November, subject to weather and operational constraints.
The survey will use one geophysical survey vessel, up to four remotely
piloted uncrewed surface vessels (USVs) carrying geophysical equipment
and one support vessel. Hull-mounted and towed systems will be deployed,
while the USVs will operate around the clock and transmit real-time imagery
and situational awareness data via satellite.
Bellrock is being developed by Nadara in the central North Sea, around
120km east of Stonehaven. The proposed project has a planned capacity of
up to 1.8GW, and its Wind Farm Development Area consent application was
submitted in April 2026.