Vattenfall begins offshore foundation installation for Nordlicht wind farm

Vattenfall/ Kriegers Flak ©


Vattenfall has installed the first monopile for its Nordlicht offshore wind project in the German North Sea, marking the start of offshore construction for Germany's largest offshore wind development.


The foundation was installed by DEME, who were responsible for transporting and installing the monopiles and transition pieces for both
Nordlicht I and Nordlicht II. The monopiles are now being manufactured by EEW Special Pipe Constructions in Rostock, with transition pieces being produced by CSWind in Aalborg.

Once complete, Nordlicht I will consist of 68 monopile foundations, each measuring up to 80.5 metres long and weighing as much as 1,290 tonnes.


Located north of Borkum, the Nordlicht cluster will have a combined capacity of around 1.61 GW once fully operational in 2028.


Project Director Cyril Moss said the installation marked an important milestone for the project and would support Europe's energy transition.


For more information about offshore wind farm projects across the globe, click here.