Five Estuaries Project Manager Update - February 2023
-
2 March 2023
-
-
Five Estuaries

I am pleased to announce that on 14 March
we will be launching the Five Estuaries Stage 2 Consultation. During the
consultation the Project will provide various opportunities for you to
find out more and to provide your feedback on our proposals. This statutory
stage of consultation will last for just over 8 weeks, closing on 12 May
2023. Our Preliminary Environmental Information Report (PEIR) is the first
main, detailed output of the Environmental Impact Assessment process and
will be the focus of this consultation. It sets out the potential environmental
impacts of the project, both negative and positive, based on our initial
assessments. The PEIR also proposes mitigation measures to prevent or minimise
any negative impacts identified.
During the consultation we will be holding a number of public drop-in events
across Tendring, Essex, the Suffolk coast and one in Margate, Kent. We
will also be holding two webinars, one focused on onshore elements of the
Project and one focused on offshore. We invite you to attend in person,
or virtually, to view our proposals and speak to the team to find out more
about the Project. Feedback on our plans and specific consideration based
on local knowledge is important to us and supports the refinement of our
proposals before we submit our DCO application, expected to be at the end
of 2023.
Earlier this month we published our Statement of Community Consultation
(SoCC). The SoCC explains how we intend to consult with the local community
on our proposals for the Project during this statutory stage of consultation,
as required by Section 47 of the Planning Act 2008.
View
the Statement of Community Consultation here.
Hard copies of the SoCC have been made available to view at various locations
across Essex and Suffolk. Click
here to view these locations.
Full details of the consultation, the consultation documents and how you
can provide your feedback will be available from 14 March. We will provide
an update with more information then and hope to see you at one of our
public information events.
Umair Patel
Five Estuaries Offshore Windfarm Project Manager
Onshore Surveys
In March we plan to commence some ground investigation surveys in selected
locations along the onshore cable route as agreed with the relevant landowners.
This is to further our understanding of ground conditions and inform ongoing
engineering design.
Land Interest Questionnaires
Land Information Questionnaires (LIQs) have been distributed by our land
agents Dalcour Maclaren. The LIQs will help to identify people who may
have an interest in land associated with the project. If you have received
a LIQ, we encourage you to complete and return this as soon as possible,
to help us make sure we communicate with the right people with an interest
in land relevant to our proposals.