Crown Estate launches accelerated tender for 1.5GW Morgan offshore wind site
-
27 July 2026
-
Government, Windfarms
-
The Crown Estate

The Crown Estate
has launched an accelerated competitive tender to appoint a new developer
to build and operate the up to 1.5GW Morgan offshore wind farm in the Irish
Sea.
The project was
returned to The Crown Estate after its previous developers discontinued
development earlier this year. Morgan and the neighbouring Mona project
had not secured Contracts for Difference (CfD) in the UK’s seventh allocation
round, with EnBW citing supply-chain cost increases, higher interest rates
and project delivery risks among the factors affecting their economic viability.
Morgan secured
development consent for its offshore wind farm assets in August 2025 and
has a grid connection agreement with the National Energy System Operator.
A decision on the joint Morgan and Morecambe transmission assets application
is expected in September 2026.
Bids are expected
to be submitted over the summer, followed by a rising clock auction. The
Crown Estate aims to select a preferred bidder towards the end of 2026.