Ørsted and PGE start offshore installation at Baltica 2

Van Oord ©


Ørsted and PGE have begun installing offshore foundations for the 1.5 GW Baltica 2 offshore wind farm in Poland.


The first monopiles have been installed in the Polish Baltic Sea as full-scale offshore construction begins on the project.


Van Oord is carrying out the foundation installation campaign, which will include 111 monopiles: 107 for wind turbines and four for offshore substations.

The installation campaign is scheduled to continue until the fourth quarter of 2026.

Baltica 2  will be located approximately 40 km off the Polish coast, near Ustka, and is expected to be fully commissioned by the end of 2027.
The project is being developed in a 50/50 partnership between Ørsted and PGE Polska Grupa Energetyczna.


Once complete, Baltica 2 is expected to generate 5–6 TWh of electricity annually, enough to supply around 2.5 million Polish households.

The wind farm will comprise 107 Siemens Gamesa 14-222 turbines, with turbine installation to be carried out by Cadeler and Fred. Olsen Windcarrier.